9 1/2 Weeks To Go To Substantial Completion Deadline
Riley: Night work on Riley will continue this evening (Thursday). Due to some plan changes, work will continue on Riley Sunday and Monday nights. No parking is allowed on the corners of the Riley/Sutter Intersection by Mélange and the Hotel in order to allow work to continue. Night Work hours are typically 8PM to 6AM
700 block: Water underground continues during the day through the remainder of this week and next. Shed roof demolition will begin on the 700 block as early as Thursday 9/17. Merchants and building owners should remove any personal items or signage attached to their shed roof no later than Thursday.
Wool Street: Work continues on the Storm drain at the intersection of Wool and Sutter. This work will continue through next week. They are working down Wool, and plan to be on lower Wool by the Chamber of Commerce on Wednesday next week. This work continues in daylight hours and Wool Street will be closed during working hours.
800 block: PG&E is finishing installation of gas services. They are scheduled for completion on Tuesday, 9/14. Once completed, Teichert will connect downspouts to buildings, at night. Once these are connected, the next step is grading for the new concrete and forming for concrete. Starting Monday 9/13, Teichert will demolish the road where the new concrete extends into the roadway in the 800 block in order to begin the remaining concrete work. This work will be take place during the day.
Hop Sing Restaurant basement is undergoing repairs now and through next week.
900 block:Starting Monday 9/13, Teichert will demolish the road where the new concrete extends into the roadway in the 900 block in order to begin the remaining concrete work. This will be happening during the day.